Rocky Point Union Free School District District | Capital Projects Update

Capital Projects Update

As part of the district’s commitment to preserve the integrity and operational efficiencies of the buildings and grounds, the following capital improvement projects have been approved by voters and will be completed in the coming years. Please be sure to check this page often for updates on these projects, including photos from all phases of construction.

 

 

Bond Work Breakdown By Building

 

Districtwide

  • Remove asbestos floor tile
  • Install door-ajar security system
  • Parking lot paving/curbing at multiple sites
  • Install Building Management System
  • Install clock and public address system
  • Replace fire panels/CO detectors
  • Update security systems, including
  • cameras and door access systems
  • Install energy-efficient ceilings and lighting

 

FJC

  • Replace HVAC system
  • Repair south portable roof
  • Renovate bathrooms, several to meet ADA compliance
  • Install AC in cafeteria

 

JAE

  • Replace boilers, burners, old piping throughout
  • Replace interior doors
  • Replace old gym windows
  • Renovate bathrooms, several to meet ADA compliance
  • Install AC in cafeteria
  • Update cafeteria
  • Install ADA wheelchair access to stage
  • Relocate music room to main floor
  • Replace cafeteria equipment
  • Reconstruct library
  • Repair masonry cracks
  • Renovate roof

 

MS

  • HVAC system enhancement
  • Install building alarm system
  • Install AC in cafeteria
  • Renovate band room
  • Water seal exterior of building

 

HS

  • Renovate bathrooms, several to meet ADA compliance
  • Renovate wrestling room
  • Renovate locker room
  • Replace original hot water tank
  • Renovate tennis courts
  • Install AC in auditorium
  • Reconstruct HS Lower Field (synthetic turf)
  • Renovate band room
  • Reconstruct existing parking lots