Capital Project Updates
HS Project Updates
August 29 Update
The new AC unit now hangs on the ceiling in the wrestling room and
accompanying ductwork is in place to feed condition air in the space
while new LED lighting has been installed throughout the wrestling room.
The final electrical and mechanical connections have been made to the
rooftop AC units, which are now officially up and running.
August 18 Update
A new electrical panel has been installed in conjunction with the
auditorium’s new air conditioning system. The steel dunnage legs as well
as the AC ductwork stands have been permanently flashed in with the new
roofing. Three new fresh air returns have been installed in the
auditorium, one behind the stage and two on the ceiling.
August 14 Update
The new tennis courts have been painted and stripped and new nets have been installed. The conduits now run from the rooftop down to the main panel in the basement to feed power to the new rooftop AC units. New circular HVAC supply diffusers are being installed in the auditorium ceiling and the new rooftop AC units are being rigged onto the auditorium roof and set on the new steel dunnage.
August 7 Update
The fencing and gates have been installed around the new tennis courts,
which have been painted with the exception of the final striping. The
steel dunnage has been installed on the auditorium roof in preparation
for the new rooftop AC units. A portion of the parking lot east of the
tennis courts has been excavated to install new drainage pools, which
will receive rainwater runoff from the tennis courts.
July 31 Update
Post-abatement air testing has been completed, which yielded 100% clean
results. The VCT flooring and vinyl base has been completed in the
abated classrooms. A structural steel was lifted onto the auditorium
roof to provide a structural platform to set the new rooftop AC units
on. Structural blocking has been installed for the proper mounting of
the HVAC roof curbs on the auditorium. A new egress door for the nurse’s
office has been hung and detailed.
July 21 Update
The tennis courts have been paved, a secondary means of egress doorway
has been installed in the nurse’s office and the installation of VCT
flooring has commenced.
July 14 Update
The tennis court construction continues and the installation of the new
smoke detectors throughout the auditorium has commenced. The rooftop
ductwork continues to be prepared for the installation of the AC unit.
Additionally, negative air units set for VAT abatement in the second
flood classrooms and the testing equipment units were assembled.
July 7 Update
Rooftop ductwork installation continues, the auditorium ceiling has been
cut to receive new AC diffusers and a new concrete curb at the tennis
court has been poured.
June 30 Update
The district started work on the tennis court demolition, including the removal of the fencing and asphalt paving. Additionally, the district began preparing the site for air conditioning installation in the auditorium and has put protective covering over the seats and RTU duct work on the roof.