Capital Project Updates
MS Project Updates
August 29 Update
The glass window has been installed in the security booth at the main
entrance and is now complete and ready for the opening of school.
August 18 Update
The new door at the MS security booth and the new nurse’s office egress
door have been installed. The welcome window [C1] has been framed in,
awaiting the installation of new glass.
August 7 Update
The new security booth has been painted.
July 31 Update
The new security booth has been sheetrocked and spackled.
July 21 Update
The new security booth has been framed.